Agenda
Deliverables due this week:
	- Finalize refresh, snapshot, landscape plan - Ron & Frank
 
	- Confirm business owners - Rita, Mary Ellen, Lee, Frank, Ken
 
	- Detailed project plan - Bart
 
	- Add team to daptiv project - Bart
 
	- SIT preparation - discuss
 
Completed last week(s):
	- High level schedule
 
	- Teams, roles, responsibilities
 
	- Core Team kick off
 
	- Created Daptiv project request
 