Key dates
Support Pack Project
- Now - October - Plan, create master script catalog, improve test scripts, move pending work to production
 - 10/05/2009 - Last date to implement projects until freeze ends on 12/24/2009 (Except Open Enrollment & Union Structures)
 - 10/22/2009 - Last date to implement support & enhancement changes until freeze ends on 12/24/2009
 - 11/09/2009 - 11/22/2009 System Integration Test
 - 11/23/2009 - 12/09/2009 User Acceptance Test
 - 12/11/2009 - 12/13/2009 Golive Weekend
 - 12/24/2009   Freeze ends ends
 
Open Enrollment & Union Structures
- 09/15/2009 - 10/01/2009 System Integration Test
 - 10/01/2009 - 10/31/2009 User Acceptance Test
 - 11/02/2009 - 11/06/2009 Pilot Open Enrollment
 - 11/09/2009 - 11/20/2009 Community Open Enrollment
 - 12/06/2009   Vendor Extracts
 
Summary Plan

Monthly Priorities & Deliverables
...
 
    
    
            
 
    
    
    
    
    
    
    
    
        
            
            
    
    
        
            
            
    
 
 
 