Key dates

Support Pack Project

  • Now - October - Plan, create master script catalog, improve test scripts, move pending work to production
  • 10/05/2009 - Last date to implement projects until freeze ends on 12/24/2009 (Except Open Enrollment & Union Structures)
  • 10/22/2009 - Last date to implement support & enhancement changes until freeze ends on 12/24/2009
  • 11/09/2009 - 11/22/2009 System Integration Test
  • 11/23/2009 - 12/09/2009 User Acceptance Test
  • 12/11/2009 - 12/13/2009 Golive Weekend
  • 12/24/2009   Freeze ends ends

Open Enrollment & Union Structures

  • 09/15/2009 - 10/01/2009 System Integration Test
  • 10/01/2009 - 10/31/2009 User Acceptance Test
  • 11/02/2009 - 11/06/2009 Pilot Open Enrollment
  • 11/09/2009 - 11/20/2009 Community Open Enrollment
  • 12/06/2009   Vendor Extracts

Summary Plan

Monthly Priorities & Deliverables

...